【每日一练】CFA 一级(2015年)

Question:

A company that uses International Financial Reporting Standards (IFRS) entered into a three-year construction project with a total contract price (all figures in thousands) of $5,300 and expected costs of $4,400. At inception, the outcome of the contract could not be reliably measured, but the company did expect to recover its costs. Actual results are shown in the following table: 

The amount of revenue (in thousands) the company recognized in Year 2 was closest to: 
A. $0.
B. $2,409. 
C. $2,000. 
 

 Answer = C 

Under IFRS, if the outcome of the contract cannot be reliably measured, but the company expects to recover its costs, then revenue may be recognized to the extent of the contract costs incurred. In Year 2, the costs incurred were $2,000 thousand, thus, the revenue would also be $2,000 thousand and the gross profit would be $0. 

CFA Level I 
"Understanding Income Statements," Elaine Henry and Thomas R. Robinson 
Section 3.2.1 

 

 

CFA特许金融分析师1-3级【沪江金程联合开发】

19年12月-22年6月考季的考生,助力通过金融第一考

查看折扣

CFA1级1912考季【沪江金程联合开发】

权威名师倾情打造,助力通过金融第一考

查看折扣

金融英语【沪江金程联合开发】

为零基础学员提供学习指导

查看折扣

更多精彩:

工作后适合考CFA吗?在职如何备战CFA考试?

CFA证书与985学历相比,真的更好用吗?

相关课程 更多课程

日语零基础直达N1【签约班】

免费试听

日语零基础直达N1【畅学班】

免费试听

日语全程直播课-超值启航卡(1年)

免费试听

日语零基础直达N1【经典班】

免费试听

日语0-N1全程直播班

免费试听

日语N2直达N1【签约班】

免费试听

日语N1考前强化

查看详情

日语全程直播课-至尊卓越卡(3年)

免费试听

日语能力考1V1【私人定制】

查看详情

相关阅读